| 07/15/04 |
16:00 |
12m |
The old Sun workstations were removed today and we installed
the new Linux boxes. Corona, Tecate, Ballena, and Locura were replaced. We
now begin the process of recompiling the control system software for Linux. |
News |
| 07/14/04 |
16:00 |
12m |
The new 40 KVA UPS for Kitt Peak 12 Meter has been installed
and now awaits the factor rep's inspection and initial tests. |
News |
| 07/06/04 |
8:00 |
SMT |
There has been a tremendous amount of activity regarding the
Nuttall Fire Complex on Mt. Graham. Click the
here to go to our web
page containing the latest news and information regarding this fire. |
News |
| 07/02/04 |
17:00 |
SMT |
The MGIO site was ordered evacuated at 17:00 MST today. The
Gibson fire went from 10 acres to to more then 100 acres in just a few hours
forcing all personnel off the mountain.
More... |