12 Meter Summer Shutdown 2003


 

       
Jobs Delegated To Dates Pri
       
Inspect & Repair Dome Wheels & Tires George et al July 31 - Sept 01 1
Inspect & Repair Dome Door Rollers & Sprockets George et al July 31 - Sept 01 1
Inspect & Repair Dome Arch Beam George et al July 31 - Sept 01 1
Inspect & Repair Dome Power Track George et al July 31 - Sept 01 1
Inspect & Repair Dome Drive Motors & Brushes George et al July 31 - Sept 01 1
Lubricate Entire Telescope & Dome George et al July 31 - Sept 01 1
Inspect MG's & Brushes George et al July 31 - Sept 01 1
Drain all gear boxes and install new oil George et al July 31 - Sept 01 1
PM on Nova UPS's & Batteries George et al July 31 - Sept 01 1
Finish painting Dome Door with Cool-Kote. George et al July 31 - Sept 01 1
Change weight cage to the same bottom as Rx George et al July 31 - Sept 01 1
Clean Dome Door George et al July 31 - Sept 01 1
  George et al July 31 - Sept 01 1
Inspect & Repair Dome carbons George et al July 31 - Sept 01 1
Inspect & Tighten all Dome Electrical Connections George et al July 31 - Sept 01 1
Clean Telescope & Re-grease Operators July 31 - Sept 01 1
       
Clean & Repair Control Room Fans & Filters John July 31 - Sept 01 2
PM on Transtector Jon July 31 - Sept 01 2
Clean All AC Ducts and Filters John July 31 - Sept 01 2
Pressure Wash Dish, Dome & Floor Operators July 31 - Sept 01 2
Paint Dome Walls & Floors Operators July 31 - Sept 01 2
Repair Library & Observer Dorm Siding Operators July 31 - Sept 01 2
Replace Onan Batteries George et al July 31 - Sept 01 2
       
Repair tipper and reinstall. Jon/William July 31 - Sept 01 1
Repair Spectrum Analyzer and reinstall. Jon July 31 - Sept 01 1
Ventilate Filter Banks and Power supplies. George July 31 - Sept 01 1
Repair and reinstall 2 meg filters. William July 31 - Sept 01 1
Repair and reinstall dish camera. William July 31 - Sept 01 2
Repair or replace Nova UPS's. Tom/Aldo July 31 - Sept 01 1