SMT Summer Shutdown 2003


           
Job # Done? Category Job/Description Who ? Priority
           
Buliding:          
1 NOT Mech Man lift for door seals Steve 1
2 Working Mech Roof & door seals Steve 1
3   Mech Seal door on 5th floor Steve 1
4 Working Mech Widen door between receiver rooms Steve 1
5   Mech Install hatch in receiver room Steve 1
6 Done Mech Seal vents Steve 1
7   Mech Install taumeter cover Steve 1
8 Done Mech Fireproof building Steve 2
9   Maint Reinstall drywall Steve 2
10 Done Mech Fix rubbing hydro cylinder Steve 2
11   Maint Paint fourth floor Steve 3
12 Done Mech Hydraulic service Steve 1
13 Done Maint Clean track. All 1
14   Mech Adjust building wheels Steve 1
15   Maint Crane maintenance Steve/Harry 1
16   Mech/Elec Fans in 5th floor walls Steve 2
17   Mech/Elec Building drive tests Harry et al 2
18   Electrical Heat tape checks and mods Harry 2
19   Electrical UPS to 5th floor Harry 2
20 Done Electrical Install light in chiller room Steve 3
21   Electrical Door and roof limit switches Steve/Harry 1
22   Electrical Install new weather station Steve 2
23   Electronic Building drive current signals- find noise source. Pete 1
24   Electronic Check for Building ground loop's. Pete 1
25   Program Measure (& log?) building currents. Pete/Tom 2
           
Telescope:          
26 Done Mech Inspect and grease hot-vane slider. Steve et al 1
27   Mech Calibrate building vs antenna limit switches.. Steve/Harry 1
28   Electrical Rewire Krupp for LED's. ? 1
29   Mech Check elevation wrap Steve 1
30   Program Check out inclinometers. Bill/Pete 2
31   Electronic Inclinometer low pass filter -PCB and hook up temp sensor. Pete 1
           
Peir:          
32 Done Mech Clean and grease Az and El bearings Steve et al 1
33   Mech Clean & grease ring gear Steve 1
34   Mech Grease elevation motors Steve 1
35   Mech Check Az wrap for cable wear. Steve 2
           
Control System:          
36 Done Admin Back up all observers data / user areas Tom 1
37 Working Admin Upgrade all Non-Realtime Linux boxes to RH7.3 Tom 1
38 Working Admin Get all Linux boxes on RHN Tom 1
39 Done Admin Install firewall Tom 1
40 Done Admin Identify any bad scsi disks on tux and replace or repair. Tom 1
41 Done Admin Find a permanent home for smtotux Tom 2
42 Working Program Clean up CACTUS_GLOBAL. Tom 1
43   Program Install receiver fuctions in global memory. Tom 1
44   Program Install and program zero check box on VCO's Pete/Tom 1
45 Started Program Finish IF routing and software on FMS Pete/Tom 1
46 Working Program Order and install new FMS mother board Tom 1
47   Program Finish 'goodness of fix' function in five points. Tom 2
48   Program We need an 'Ignore Offsets' button in Rambo Spec 5 screen Tom 1
49   Program Allow accepting individual channels in fits. Tom 2
50   Program Rambo should indicate it's taking data. Tom 2
51   Program Line name into headers Tom 1
52   Program Spec 5 offsets are not in class files. Tom 1
53   Program Inproper beams alarm. Tom 1
54   Program Fix Tipper going below tree line? Tom 2
55   Program Put final touches on remote observing package. Tom 2
56   Admin Finish remote observing document Tom 2
57 Done Program Port UPSsuck, WeatherSuck, and WindSuck. Bill 1
58   Program Port Tipsuck. Bill 1
59   Program Port FitIncRealtime Bill 1
60 Done Admin Download the terminal servers from Linux. Bill 1
61   Program Log sun distance and angle. Tom 2
62 Done? Program SAMBUS channels 27-31 (+ ...) don't work. Bill/Pete 2
63 Done Program What about spontaneous 0x80 bit? Bill/Pete 2
64 ---- Program Get latching mode to work in VxWorks 0-15 Bill/Pete 2
65 Done Admin Turn on Linux xdm server for X-terminals. Bill 2
66   Program Remember focus & pointing settings between receiver changes. Tom 1
67   Program Clean out unneeded log messages, especially msg's to Monitor. Tom/Bill 2
68   Program Log encoder fit parameters vs angle. Tom S/Tom 2
69   Program Log encoder zero point resets and fiducial encounters w/o reset. Tom S./Tom 2
70   Program Make successive tracker polynomials join at the ends. Tom S. /Bill 1
71   Program Check out tracking at high elevation and high speed (holo) Tom S. /Bill 1
72   Program Make servo work with both elevation encoders. Tom S. 1
73   Program More Testing of Sun Avoidance. Tom S. 1
74   Program Servo recoverery during drive cycling. Tom S. 1
75   Program Port NETCHECK. Bill 2
76   Program Install raster scanning pointing. Tom/Bill 2
77 Working Program Configure and Install displays in kitchen and lounge. Tom 1
78   Admin Upgrade Autocad on mountain. Carlson 2
79   Program Add VATT weather info to our displays. Tom 3
80 Done Program Clean up 'mailboxdefs' file Tom 1
81   Program BSCAL should not be done on source. Tom 1
82   Program Add Vane temperature to GLOBAL Tom 1
83 Done Program Rewrite mailboxdefs file Tom 2
           
           
Prime Focus:          
84   Computing Install sensors on focus translation stage and quadrapod. Bob S./Tom 1
85   Computing Thermal test on Sub-Reflector? ? 2
86   Computing Check sun limits and for heating of focus translation stage. Tom/Bill/Tom 1
87   Computing Move the lower limit switch on Focus Motor #1 0.3 mm or so. ? 2
88   Mech Subreflector Work ( remove from telescope) Steve/Harry 1
89   Maint Touch up paint work on quadrapod ? 2
90   Mech Optical telescope tests Tom 3
91   Computing Pinhole camera tests Bill et al 1
92 Working Computing Get Optical focus to work w/o laptop. Tom 1
93 Working Computing Get Optical pointing mode up w/o twf. Tom 1
94   Computing Get Optical focus stage with more range? ? 2
           
Receivers:          
95   Receiver Cold Head maintenance Martin 1
96   Receiver Compressor repairs and modifications Martin 2
97   Receiver Install 2mm JT receiver Harry 1
98   Receiver Tuning tests, 345 GHz Harry 2
99   Electronic Bias Box modifications 460 GHz Harry 2
100 Done Receiver Change oil in vacuum pump Steve 2
101   Electrical Install power for compressor Steve 2
102   Mech Repair light tower limit switch. Pat 1
           
Backends/IF:          
103   Electronic Filter Bank tests and repairs Harry 2
104   Electronic Chirp Downconverter mods (2.1 GHz IF ) Harry 1
105   Electronic New cables for the Backend Switch Box Martin 2
106 Working Electronic IF back end box; Finish instillation. Pete 1
107 Working Electronic VCO Zero box- PCB and construction. Pete 1
108 Working Electronic Encoder power supplies- Change to external 115 Volts.. Pete 1
109 Working Electronic New Encoder amplifier boards- PCB layout and construction. Pete 1
           
Misc:          
110   Electronic 10 MHz Distribution noise tests Harry 2
111   Electronic Temperature monitor for Maser Room Harry 3
112   Mech Siding on Hilton Steve 2
113   Mech Clean Basecamp container Steve 3
114   Mech Purchase and install weather station box. Robert 2
115 Done Purchase Purchase and install new audio system. Bill Hale et al 3
           